# Approvals - Request change should keep the task incomplete

**URL:** <https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962>\
**Category:** Features Launched\
**Tags:** launched\
**Created:** [10 March 2020 09:02 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962 "2020-03-10T09:02:07Z")\
**Posts on this page:** 20\
**Page:** 2

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [25 November 2022 16:35 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/21 "2022-11-25T16:35:12Z")

</div>

Welcome, @anon49335325,

Don’t forget to vote for your request!

Until/if Asana makes such a change, consider using this approach in the meantime (if you haven’t already):

> [@A new type of task is available in Asana. Meet Approvals!](https://forum.asana.com/t/a-new-type-of-task-is-available-in-asana-meet-approvals/72774/7):
>
> I haven’t used Approvals much yet, but… What initially occurred to me upon hearing that all approvals mark the task complete was: So then I would want the approval to be a separate task–not apply on the actual work task itself And maybe this added approval task could be 1) a subtask of the actual work task to keep them together (and facilitate multiple approvals should the need arise), or 2) a follow-up task And/Or make the actual work task dependent on the approval. Just thinking out loud, …

Larry

---

<div class="post-metadata">

**Author:** ![Marina\_Rebelo](https://luna1.co/8d76cd.png) [@Marina\_Rebelo](https://forum.asana.com/u/Marina_Rebelo)\
**Post date:** [27 November 2023 12:53 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/22 "2023-11-27T12:53:59Z")

</div>

Tasks that requires approval when marked as ‘changes needed’ or ‘ready for rewiew’ should not be considered a ‘completed task’, since it is not!

---

<div class="post-metadata">

**Author:** ![Danielle-GenD](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/danielle-gend/32/220420_2.png) [@Danielle-GenD](https://forum.asana.com/u/Danielle-GenD)\
**Post date:** [27 November 2023 13:09 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/23 "2023-11-27T13:09:57Z")

</div>

Hi @Marina_Rebelo welcome to the forum! There is much debate around this. Technically if the task is an approval task one it has been approved, changes requested or denied then the approval is considered complete.

Best practise is by adding an approval sub task to the main task itself so the approval is completed and not the task requiring approval

---

<div class="post-metadata">

**Author:** ![Danielle-GenD](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/danielle-gend/32/220420_2.png) [@Danielle-GenD](https://forum.asana.com/u/Danielle-GenD)\
**Post date:** [27 November 2023 13:24 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/24 "2023-11-27T13:24:23Z")

</div>

Or alternatively you could use a single select custom field instead with the options Approved, Changes requested etc that whomever is approving changes and then adds comments to the main task

---

<div class="post-metadata">

**Author:** ![Marina\_Rebelo](https://luna1.co/8d76cd.png) [@Marina\_Rebelo](https://forum.asana.com/u/Marina_Rebelo)\
**Post date:** [27 November 2023 13:52 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/25 "2023-11-27T13:52:15Z")

</div>

Well, this is no solution, adding a task for approval is retroactive in process organization. From what I have seen, this is an old request, almost 4 years, and still remains the same.

---

<div class="post-metadata">

**Author:** ![Benito\_Segovia](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/benito_segovia/32/22574_2.png) [@Benito\_Segovia](https://forum.asana.com/u/Benito_Segovia)\
**Post date:** [5 December 2023 22:07 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/26 "2023-12-05T22:07:58Z")

</div>

> Technically if the task is an approval task [one] it has been approved, changes requested or denied then the approval is considered complete.

So what is the official recommendation when changes are requested? Duplicate the task and pick up the conversation there?

e.g. “Task 1: Design payment form” \> Marked for Approval (by designer) \> Marked as “Changes Requested” with comments \> task disappears from “Incomplete Lists” \> Duplicate Task with updated title “Task 1 Round 2: Design payment form” \> repeat.

---

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [6 December 2023 05:37 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/27 "2023-12-06T05:37:38Z")

</div>

A couple options are either 1) When using approval-type tasks, specify them as subtasks of the task to which they apply (see my earlier post above), or 2) don’t use approval-type tasks (see @Danielle-GenD’s post above).

Thanks,

Larry

---

<div class="post-metadata">

**Author:** ![Riah](https://luna1.co/8d76cd.png) [@Riah](https://forum.asana.com/u/Riah)\
**Post date:** [13 December 2023 20:34 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/28 "2023-12-13T20:34:06Z")

</div>

seeing that this has been common topic since 2020 is honestly disappointing! we should not have to add _another_ subtask, _another_ custom field. too many tasks and fields is just overstimulating, messy, and hard to keep track of.

I have two different rules set up:

1. Approval status set to “ **Approved** ” – task marked as “ **Complete** ” + moved to “ **Complete** ” – Asana Bot comment " @(_collaborators_) Content for (_posting date_) has been Completed! Download the files attached."

2. Approval status set to “ **Changes Requested** ” or “ **Rejected** ” – task marked as “ **Incomplete** ” + moved to “ **In Progress** ” – Asana Bot comment " @(_Assignee_) Changes requested on content for (_posting date_). Please update with team feedback notes by (_due date_)."

when a task is set to “Changes Requested” BOTH rules run – even though they are specified by different approval statuses?? even if i unmark “this rule can be triggered by other rules”.

the current way of approvals is not ideal for a successful workflow. we pay for Asana for _ease_ – to cut down on things that take up our time. I am in Los Angeles CA and my teammate is in London UK, other coworkers in the East Coast. Asana is meant to help our content feedback and work process, and it seems this is something many people have an issue with for the last four years. also it _literally_does not make sense. if you ask for something to be changed, it is not finished.

---

<div class="post-metadata">

**Author:** ![Shayan\_Moussawi](https://luna1.co/8d76cd.png) [@Shayan\_Moussawi](https://forum.asana.com/u/Shayan_Moussawi)\
**Post date:** [26 February 2024 14:35 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/29 "2024-02-26T14:35:45Z")

</div>

I tried implementing Approval Tasks into our workflow - but have found them to be a useless feature.

They do not serve any purpose other than a visual indication and they come with a major caveat:

- Tasks with the stage “changes requested” or “rejected” are considered ‘complete’ hence do not appear in the assignees “My tasks” or cannot be easily filtered by in a project

We are trying to use approvals as part of a standard agile approval process, at the end of a sprint:

- Turning the Sprint tasks into an approval tasks
- marking the task as “changes needed” with Feedback in the comments if not approved

I do not see the benefit or difference, over simply using a custom field for the Review stage - as this custom field is needed anyway if we want to filter by the tasks in a project, or have them appear under “my tasks”.

Tasks which were not approved should hence, not be considered complete - as there still is an active to do.

---

<div class="post-metadata">

**Author:** ![Shayan\_Moussawi](https://luna1.co/8d76cd.png) [@Shayan\_Moussawi](https://forum.asana.com/u/Shayan_Moussawi)\
**Post date:** [26 February 2024 14:38 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/30 "2024-02-26T14:38:19Z")

</div>

Additionally because not approved tasks are considered complete - dependencies will not work with them

---

<div class="post-metadata">

**Author:** ![Jeremy\_Jensen1](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/jeremy_jensen1/32/73872_2.png) [@Jeremy\_Jensen1](https://forum.asana.com/u/Jeremy_Jensen1)\
**Post date:** [26 February 2024 18:25 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/31 "2024-02-26T18:25:21Z")

</div>

yeah if changes are needed/requested the task is still in progress and not fully completed successfully.

---

<div class="post-metadata">

**Author:** ![Kathryn\_Wirtz](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/kathryn_wirtz/32/98993_2.png) [@Kathryn\_Wirtz](https://forum.asana.com/u/Kathryn_Wirtz)\
**Post date:** [18 March 2024 14:08 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/32 "2024-03-18T14:08:35Z")

</div>

It seems useless that the “Approval” feature indicators all mark the task complete - even if there are changes needed. That doesnt make sense to me. Can their be other options instead of just completing the task immediately?

---

<div class="post-metadata">

**Author:** ![Larry\_Berger\_lpb](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/larry_berger_lpb/32/276017_2.png) [@Larry\_Berger\_lpb](https://forum.asana.com/u/Larry_Berger_lpb)\
**Post date:** [18 March 2024 18:23 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/33 "2024-03-18T18:23:29Z")

</div>

Welcome, @Kathryn_Wirtz,

I’ve merged your post into an existing thread where you can click the title to scroll to the top and vote by clicking the purple Vote button.

There are workarounds in the thread, but briefly, a best practice is to make Approvals subtasks of the work they apply to. Consider the approval a very narrowly-scoped action; the act of designating that approval choice completes the action. I think that’s the intent of the design of the feature.

Thanks,

Larry

---

<div class="post-metadata">

**Author:** ![Jeffrey\_Marler](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/jeffrey_marler/32/252866_2.png) [@Jeffrey\_Marler](https://forum.asana.com/u/Jeffrey_Marler)\
**Post date:** [2 August 2024 15:52 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/34 "2024-08-02T15:52:01Z")

</div>

+1, My team uses automation on our milestones in projects that close milestones when all the dependencies are completed. having to manually go back and undo items because a rejection falsely completed a milestone is tedious.

---

<div class="post-metadata">

**Author:** ![Eli\_Arbreton1](https://luna1.co/8d76cd.png) [@Eli\_Arbreton1](https://forum.asana.com/u/Eli_Arbreton1)\
**Post date:** [12 November 2024 18:04 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/35 "2024-11-12T18:04:47Z")

</div>

Currently doing the “[workflow specialist certificate](https://academy.asana.com/path/asana-workflow-specialist-certificate)” and there is a rule that shows up as an example in the course where an approver choosing “request changes” would break the workflow.

The workflow in the course includes the two rules at the top of the following image:  
_(reference: “lesson: workflow specialist certificate \> build:optimize your workflow \> topic 12 of 13”)_

 ![Frame 1](https://us1.discourse-cdn.com/asana/original/4X/9/d/8/9d8861645eff478539d6232016d9f11131b043b3.png)

If the reviewer chooses the option “request changes” then the automation to complete the main task will trigger because the marking “request changes” counts as changing the task completion status to complete on the back end. This would result in moving the ticket to the complete section, even though there are still changes that need to happen.

I ran into a similar issue when creating workflows for my team and our solution was to avoid ever choosing the options “request changes” or “rejected” but then there was no point in using an approval subtask rather than a regular subtask.

When experimenting with rules I did find a **potential solution** (the rule at the bottom of the image above) but this solution will likely only work for workflows that reassign the main task rather than assigning [multiple] approval subtask[s].

The designer could then trigger the approval rule (not shown here) again to reassign to the approver.

_Sorry for the weird formatting. I was only allowed one embed since I’m a new user._

---

<div class="post-metadata">

**Author:** ![Yvonne\_R\_Muller](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/yvonne_r_muller/32/89701_2.png) [@Yvonne\_R\_Muller](https://forum.asana.com/u/Yvonne_R_Muller)\
**Post date:** [15 November 2024 21:23 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/36 "2024-11-15T21:23:58Z")

</div>

Bare minimum, a binary for triple option tasks seems counter intuitive, it almost begs for a third status of “in progress.”

I came here cause I’m looking for a way to search for “Request Changes” approval tasks in advanced search. You can select task type as approval but then the status options are not approval tasks based but general task based. So agree with everyone but also just want advanced search for this to make my life managing the selection of images and approval of copy across over a hundred events (while doing my other jobs lol)

 ![image](https://us1.discourse-cdn.com/asana/original/4X/a/2/7/a2751b972273c0568346178ea995072b9a5e9426.png)

---

<div class="post-metadata">

**Author:** ![FenwayJohnny](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/fenwayjohnny/32/147211_2.png) [@FenwayJohnny](https://forum.asana.com/u/FenwayJohnny)\
**Post date:** [18 November 2024 16:25 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/37 "2024-11-18T16:25:16Z")

</div>

Can we get an update from Asana team on this item? @Marie @Emily_Roman

---

<div class="post-metadata">

**Author:** ![Phil\_Seeman](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/phil_seeman/32/81525_2.png) [@Phil\_Seeman](https://forum.asana.com/u/Phil_Seeman)\
**Post date:** [18 November 2024 16:35 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/38 "2024-11-18T16:35:52Z")

</div>

> [@FenwayJohnny](#):
>
> Can we get an update from Asana team

Asana doesn’t comment on unannounced features so we won’t hear any updates unless/until they implement this change.

---

<div class="post-metadata">

**Author:** ![Phil\_Seeman](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/phil_seeman/32/81525_2.png) [@Phil\_Seeman](https://forum.asana.com/u/Phil_Seeman)\
**Post date:** [18 November 2024 16:38 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/39 "2024-11-18T16:38:04Z")

</div>

FYI we just added support for specific Approval statuses in our [Flowsana](https://flowsana.net) rules, so you can now “fix” this behavior with a Flowsana rule:

 ![image](https://us1.discourse-cdn.com/asana/original/4X/8/0/e/80e71282e8ba25b3a437bc0270250c67bd1ab069.png)

---

<div class="post-metadata">

**Author:** ![Ericka\_Paz](https://sea2.discourse-cdn.com/asana/user_avatar/forum.asana.com/ericka_paz/32/281714_2.png) [@Ericka\_Paz](https://forum.asana.com/u/Ericka_Paz)\
**Post date:** [19 March 2025 15:52 UTC](https://forum.asana.com/t/approvals-request-change-should-keep-the-task-incomplete/76962/40 "2025-03-19T15:52:37Z")

</div>

Recently realized that though you can establish a dependency between approvals, the “blocking” function doesn’t work. There appears to be a dependency, but approver can approve regardless of that dependency. Shouldn’t approvals have the same blocking functionality available that tasks/subtasks do?